Q1 | Concealed places that cannot be inspected

A 100 V low-voltage indoor wiring is to be installed in a dry concealed place that cannot be inspected. Which wiring method may NOT be used?

  1. Metal conduit wiring (金属管工事)
  2. Insulator wiring (がいし引き工事)
  3. Synthetic resin conduit wiring, except CD pipe (合成樹脂管工事)
  4. Cable wiring (ケーブル工事)
AnswerB. Insulator wiring (がいし引き工事)

Insulator wiring supports exposed wires on insulators, so it cannot be used in concealed places that cannot be inspected. Metal conduit, synthetic resin conduit and cable wiring can be used in every type of location if their conditions are met.

Q2 | Damp locations

A 100 V low-voltage indoor wiring is to be installed in an exposed damp place. Which wiring method may NOT be used?

  1. Metal conduit wiring (金属管工事)
  2. Cable wiring (ケーブル工事)
  3. Type 2 flexible metal conduit wiring (二種金属製可とう電線管工事)
  4. Metal raceway wiring (金属線ぴ工事)
AnswerD. Metal raceway wiring (金属線ぴ工事)

Metal raceway (senpi) wiring may be used only in dry exposed places and dry concealed places that can be inspected, so it cannot be used in damp places. Metal conduit, cable and Type 2 flexible metal conduit wiring can be used in damp or wet places.

Q3 | Lighting duct

Where may 100 V lighting duct wiring be installed?

  1. A dry exposed place
  2. A damp exposed place
  3. A dry concealed place that cannot be inspected
  4. A wet concealed place that can be inspected
AnswerA. A dry exposed place

Lighting duct wiring (300 V or less) may be installed in dry exposed places and dry concealed places that can be inspected. Damp and wet places are not dry, so they are not allowed, and concealed places that cannot be inspected are not allowed either.

Q4 | Classifying locations

Which of the following is a "concealed place that can be inspected"?

  1. The inside of a wall without an inspection opening
  2. The inside of a concrete floor
  3. The space above a ceiling with an inspection opening
  4. The surface of an indoor wall
AnswerC. The space above a ceiling with an inspection opening

The space above a ceiling with an inspection opening is hidden but can be inspected. The inside of a wall without an opening and the inside of a concrete floor cannot be seen without breaking the building, so they are concealed places that cannot be inspected. The surface of a wall is an exposed place.

Q5 | Flammable gas

Which wiring method may be used for low-voltage indoor wiring in a place where flammable gas such as propane may be present?

  1. Synthetic resin conduit wiring (合成樹脂管工事)
  2. Metal raceway wiring (金属線ぴ工事)
  3. Metal conduit wiring (金属管工事)
  4. Insulator wiring (がいし引き工事)
AnswerC. Metal conduit wiring (金属管工事)

In places with flammable gas only metal conduit wiring and cable wiring are allowed. Synthetic resin conduit is allowed (with conditions) for combustible dust and hazardous materials, but not for flammable gas. Metal raceway and insulator wiring are not allowed in places with flammable gas, combustible dust or hazardous materials.

Q6 | Combustible dust

Which wiring method may be used for low-voltage indoor wiring in a place with combustible dust such as wheat flour?

  1. Synthetic resin conduit wiring with rigid PVC conduit 2 mm or more thick
  2. Synthetic resin conduit wiring with CD pipe
  3. Insulator wiring (がいし引き工事)
  4. Metal raceway wiring (金属線ぴ工事)
AnswerA. Synthetic resin conduit wiring with rigid PVC conduit 2 mm or more thick

In places with combustible dust, synthetic resin conduit wiring (excluding pipes under 2 mm thick and CD pipe), metal conduit wiring and cable wiring are allowed. Rigid PVC conduit 2 mm or thicker meets the condition. CD pipe is excluded, and insulator and metal raceway wiring are not allowed.

Q7 | Hazardous materials

Which may NOT be used for low-voltage indoor wiring in a place where petroleum is stored?

  1. Metal conduit wiring with thin steel conduit
  2. Synthetic resin conduit wiring with rigid PVC conduit 2 mm or more thick
  3. Cable wiring with the cable in conduit or other protection
  4. Synthetic resin conduit wiring with CD pipe
AnswerD. Synthetic resin conduit wiring with CD pipe

In places that make or store hazardous materials such as petroleum, synthetic resin conduit (excluding pipes under 2 mm thick and CD pipe), metal conduit and cable wiring are allowed. CD pipe is excluded. Metal conduit, rigid PVC conduit 2 mm or thicker and cable wiring with the cable in conduit or other protection are allowed (Article 177).

Q8 | Floor duct

Which statement about floor duct wiring is correct?

  1. It may also be installed in damp or wet places
  2. It is installed in dry concealed places that cannot be inspected (inside floors) at 300 V or less
  3. It is basically installed along the ceiling in exposed places
  4. It may be used without conditions for wiring over 300 V
AnswerB. It is installed in dry concealed places that cannot be inspected (inside floors) at 300 V or less

A floor duct is embedded in the floor and is used at 300 V or less in dry concealed places that cannot be inspected. It cannot be used in damp or wet places, it is not a ceiling method, and it cannot be used above 300 V.

Q9 | Methods usable anywhere

For 100 V low-voltage indoor wiring, which method may be installed (if its conditions are met) in exposed places, concealed places that can be inspected and concealed places that cannot, whether dry, damp or wet?

  1. Metal duct wiring (金属ダクト工事)
  2. Insulator wiring (がいし引き工事)
  3. Lighting duct wiring (ライティングダクト工事)
  4. Cable wiring (ケーブル工事)
AnswerD. Cable wiring (ケーブル工事)

Cable wiring, like metal conduit, synthetic resin conduit and Type 2 flexible metal conduit wiring, can be used in every location if its conditions are met. Metal duct and lighting duct wiring are limited to dry exposed places and dry concealed places that can be inspected. Insulator wiring cannot be used in concealed places that cannot be inspected.

Q10 | Joints inside conduit

Which is an inappropriate practice in metal conduit wiring?

  1. Joining wires inside an outlet box
  2. Joining wires inside the conduit and wrapping the joint with tape
  3. Using stranded 600 V PVC insulated wire
  4. Using 600 V PVC insulated wire with a 1.6 mm diameter
AnswerB. Joining wires inside the conduit and wrapping the joint with tape

In metal conduit wiring, wires must not be joined inside the conduit; joints are made inside boxes, so a joint in an outlet box is correct. Insulated wire (except OW) that is stranded, or solid wire of 3.2 mm diameter or less, may be used, so stranded PVC wire and 1.6 mm solid wire are both fine.

Q11 | Metal conduit thickness

What is the minimum wall thickness of metal conduit embedded in concrete?

  1. 0.5 mm
  2. 1.0 mm
  3. 1.2 mm
  4. 2.0 mm
AnswerC. 1.2 mm

Under Article 159 of the Interpretation, metal conduit embedded in concrete must be at least 1.2 mm thick. Elsewhere 1.0 mm is the basic minimum, and 0.5 mm is allowed only for conduit without joints, 4 m or shorter, in dry exposed places. There is no 2.0 mm rule for metal conduit (it is easily confused with the thickness of synthetic resin conduit, 2 mm or more as a rule).

Q12 | Omitting grounding of metal conduit

In metal conduit wiring of 300 V or less, in which case may the Class D grounding of the conduit be omitted?

  1. 100 V to earth AC, 6 m of conduit in a dry place
  2. 200 V to earth AC, 6 m of conduit in a dry place
  3. 100 V to earth AC, 10 m of conduit in a dry place
  4. 200 V to earth AC, 3 m of conduit in a damp place
AnswerA. 100 V to earth AC, 6 m of conduit in a dry place

Grounding may be omitted (1) for conduit 4 m or shorter in a dry place, or (2) for 150 V or less to earth with conduit 8 m or shorter in a dry place (or with simple contact protection). 100 V, 6 m, dry fits (2). 200 V, 6 m fits neither. 10 m exceeds 8 m. Even 3 m does not fit (1) in a damp place.

Q13 | Wires in conduit

Which wire may NOT be pulled into conduit in metal or synthetic resin conduit wiring?

  1. Outdoor PVC insulated wire (OW)
  2. Stranded 600 V PVC insulated wire (IV)
  3. 600 V grade-2 PVC insulated wire (HIV)
  4. 600 V PVC insulated wire (IV), 2.0 mm diameter
AnswerA. Outdoor PVC insulated wire (OW)

Conduit wiring uses insulated wire, but outdoor PVC insulated wire (OW) is excluded. Stranded IV, HIV and 2.0 mm solid IV (3.2 mm or less) may be used.

Q14 | Supporting synthetic resin conduit

In synthetic resin conduit wiring, what is the maximum distance between supports when the conduit is fixed along building members?

  1. 1.0 m
  2. 2.0 m
  3. 1.5 m
  4. 3.0 m
AnswerC. 1.5 m

Under Article 158, supports for synthetic resin conduit must be 1.5 m or less apart. 2.0 m is the figure for cables along the underside or side of building members, and 1.0 m is for cabtyre cable, so they are easy to confuse. There is no 3.0 m rule.

Q15 | Insertion depth calculation

Two synthetic resin conduits with an outer diameter of 26 mm are joined by insertion without adhesive. What is the minimum insertion depth?

  1. 20.8 mm
  2. 31.2 mm
  3. 26.0 mm
  4. 52.0 mm
AnswerB. 31.2 mm

Without adhesive the insertion depth must be at least 1.2 times the outer diameter: 1.2 x 26 = 31.2 mm. 20.8 mm (0.8 x 26) is the value when adhesive is used. 26.0 mm (1.0 times) is not enough. 52.0 mm (2 times) is more than needed and is not the minimum.

Q16 | Installing CD pipe

Which is an appropriate way to install CD pipe (synthetic resin flexible conduit)?

  1. Running it exposed in an indoor exposed place
  2. Laying the pipe as it is above a ceiling
  3. Running it exposed on an outdoor wall
  4. Embedding it directly in concrete
AnswerD. Embedding it directly in concrete

CD pipe is not self-extinguishing and burns easily, so it must be embedded directly in concrete or placed inside a dedicated non-combustible or self-extinguishing flame-retardant pipe or duct. It cannot be left exposed indoors, above ceilings or on outdoor walls.

Q17 | Grounding flexible metal conduit

In 200 V wiring with Type 2 flexible metal conduit, when may the Class D grounding of the conduit be omitted?

  1. When the conduit is 8 m or shorter
  2. When the conduit is 4 m or shorter
  3. When the conduit is 10 m or shorter
  4. Always, regardless of length, if the voltage is 300 V or less
AnswerB. When the conduit is 4 m or shorter

Under Article 160, flexible metal conduit at 300 V or less needs Class D grounding, but it may be omitted if the conduit is 4 m or shorter. 8 m is the figure for metal conduit when conditions such as 150 V or less to earth are met. There is no 10 m rule, and at 300 V or less grounding is still required in principle.

Q18 | Solid wire size

In metal or synthetic resin conduit wiring (except short, small conduits), what is the maximum diameter of solid copper wire that may be pulled into the conduit?

  1. 3.2 mm
  2. 1.6 mm
  3. 2.6 mm
  4. 5.0 mm
AnswerA. 3.2 mm

Conduit wiring uses stranded wire or solid wire of 3.2 mm diameter or less (4 mm for aluminium). 1.6 mm and 2.6 mm are common sizes in homes, not the upper limit. 5.0 mm exceeds the limit.

Q19 | Cable support spacing

A VVF cable is fixed horizontally along the side of a building member. What is the maximum distance between supports?

  1. 1 m
  2. 1.5 m
  3. 6 m
  4. 2 m
AnswerD. 2 m

Under Article 164, cable fixed along the underside or side of building members must be supported at 2 m or less. 1 m is for cabtyre cable and 1.5 m is for synthetic resin conduit. 6 m is allowed only for vertical runs in places with contact protection.

Q20 | Cabtyre cable

When cabtyre cable is fixed along the side of a building member, what is the maximum distance between supports?

  1. 1.5 m
  2. 2 m
  3. 1 m
  4. 6 m
AnswerC. 1 m

Under Article 164, cabtyre cable must be supported at 1 m or less. 2 m is for ordinary cable, 1.5 m for synthetic resin conduit, and 6 m for vertical cable runs in places with contact protection.

Q21 | Omitting an earth leakage breaker

For a circuit supplying a 200 V three-phase motor with a metal frame, which case matches the Interpretation of the Technical Standards as one where the device that automatically breaks the circuit on a ground fault (such as an earth leakage circuit breaker, 漏電遮断器) may be omitted?

  1. The motor is installed in a wet place
  2. The Class D grounding of the motor has an earth resistance of 50 Ω
  3. The motor is installed in a dry place
  4. The circuit has a molded-case circuit breaker (overcurrent breaker, 配線用遮断器)
AnswerC. The motor is installed in a dry place

Article 36 of the Interpretation requires a ground-fault breaking device on circuits supplying low-voltage equipment over 60 V with a metal frame, but it may be omitted when the equipment is installed in a dry place. A wet place is not a reason for omission (even for equipment of 150 V or less to earth, omission applies only outside wet places). Omission based on earth resistance needs 3 Ω or less, so 50 Ω is not enough. A molded-case circuit breaker breaks overcurrent and cannot replace a ground-fault breaking device.

Q22 | Protecting cable

A cable is installed under a floor where heavy objects may press on it. Which practice is appropriate?

  1. Adding more supports so that no protection is needed
  2. Wrapping vinyl tape around the cable as protection
  3. Using a thicker cable so that no protection is needed
  4. Putting the cable in suitable protection such as metal conduit
AnswerD. Putting the cable in suitable protection such as metal conduit

Under Article 164, where cable may be under pressure from heavy objects or strong mechanical impact, suitable protection must be provided, such as metal conduit. More supports, tape or a thicker cable do not protect against crushing force and cannot replace protection.

Q23 | Joints and tensile strength

When joining wires, by what percentage or more must the tensile strength of the wire NOT be reduced?

  1. 20%
  2. 10%
  3. 30%
  4. 50%
AnswerA. 20%

Article 12 of the Interpretation requires that a joint must not reduce the wire's tensile strength by 20% or more, so at least 80% of the strength must remain. 10%, 30% and 50% are not the standard figures.

Q24 | How to join wires

Which is a correct way to join low-voltage insulated wires?

  1. Just twist the cores together without a connector and wrap tape around once
  2. Use a connector such as a ring sleeve or braze it, and cover it with insulation at least as effective as the wire's
  3. Allow the joint's resistance to increase as long as it is within the allowable current
  4. Allow weaker insulation than the wire's at the joint if the place is dry
AnswerB. Use a connector such as a ring sleeve or braze it, and cover it with insulation at least as effective as the wire's

Article 12 requires joints to use a sleeve or other device or brazing, and to be fully covered with insulation at least as effective as the wire's. Just twisting without a device is not allowed. The joint's resistance must not increase and its insulation must not be weaker.

Q25 | Joining cables

VVF cables are joined above a ceiling. Which is appropriate under the Interpretation of the Technical Standards?

  1. Joining them by a method that leaves 70% of the original tensile strength
  2. Crimping them from the outside without removing the sheath
  3. Crimping with a ring sleeve and leaving the joint uncovered with the cores visible
  4. Joining them with push-in connectors inside a junction box
AnswerD. Joining them with push-in connectors inside a junction box

Article 12 allows connectors with insulating effect, and as a rule cables are joined to each other with a junction box or other device. Using push-in connectors inside a junction box is appropriate. The joint must not reduce tensile strength by 20% or more (at least 80% must remain), so 70% is not acceptable. Crimping over the sheath does not connect the cores, so the joint would not keep the resistance from increasing. The joint must be fully covered with insulation at least as effective as the wire's, so leaving the cores visible is not acceptable.

Q26 | Ring sleeve defects

Under the practical test "criteria for defects", which is a defect in a ring sleeve joint?

  1. The core tips stick out 3 mm above the top of the sleeve
  2. 5 mm of bare core is visible below the bottom of the sleeve
  3. Using two ring sleeves for one joint
  4. All core tips can be seen when looking down into the sleeve
AnswerC. Using two ring sleeves for one joint

Using two or more sleeves for one joint is a defect. Cores sticking out above the top are a defect at 5 mm or more, so 3 mm is not. Bare core below the bottom is a defect at 10 mm or more, so 5 mm is not. Seeing all core tips from above is the correct state.

Q27 | Push-in connectors

Which is the correct state of a joint made with a push-in connector?

  1. The core cannot be seen from the side at the tip of the connector
  2. The core can be seen from the side at the tip of the connector
  3. Bare core can be seen from outside on the side where the wire enters
  4. The wire is inserted with its insulation still on
AnswerB. The core can be seen from the side at the tip of the connector

Under the criteria, if the core cannot be seen from the side at the tip, the wire is not pushed in far enough (a defect). Seeing the core means it is fully inserted. Bare core visible where the wire enters is a defect, for example from stripping too much. With the insulation on, no electrical connection is made.

Q28 | Separation from weak-current wires

What is the minimum separation between insulated low-voltage indoor wiring done by insulator wiring and weak-current wires such as telephone lines?

  1. 10 cm
  2. 3 cm
  3. 30 cm
  4. 100 cm
AnswerA. 10 cm

Under Article 167, insulator wiring must be at least 10 cm from weak-current wires. 30 cm is the figure when the wire is bare. There are no 3 cm or 100 cm rules.

Q29 | Class D grounding resistance

What is the maximum grounding resistance for Class D grounding work (D種接地工事)? Assume there is no device that automatically cuts the circuit within 0.5 seconds of a ground fault.

  1. 100 Ω
  2. 10 Ω
  3. 50 Ω
  4. 500 Ω
AnswerA. 100 Ω

Under Article 17, Class D grounding must be 100 Ω or less. 10 Ω is the value for Class C. 500 Ω applies only when a device cuts the circuit within 0.5 seconds, which is not the case here. There is no 50 Ω rule.

Q30 | Device that cuts within 0.5 s

If a device that automatically cuts the low-voltage circuit within 0.5 seconds of a ground fault is installed, what is the maximum grounding resistance for Class D grounding?

  1. 100 Ω
  2. 500 Ω
  3. 200 Ω
  4. 1000 Ω
AnswerB. 500 Ω

Under Article 17, with a device that cuts the circuit within 0.5 seconds, Class D (and also Class C) grounding may be up to 500 Ω. 100 Ω is the value without such a device. There are no 200 Ω or 1000 Ω rules.

Q31 | Class C grounding resistance

What is the maximum grounding resistance for Class C grounding work (C種接地工事)? Assume there is no device that automatically cuts the circuit within 0.5 seconds of a ground fault.

  1. 50 Ω
  2. 100 Ω
  3. 10 Ω
  4. 500 Ω
AnswerC. 10 Ω

Under Article 17, Class C grounding must be 10 Ω or less. 100 Ω is the Class D value and 500 Ω applies when a device cuts the circuit within 0.5 seconds. There is no 50 Ω rule.

Q32 | Size of the grounding wire

When annealed copper wire is used as the grounding conductor for Class D grounding, what is the minimum size set by the Interpretation?

  1. 1.0 mm diameter
  2. 1.2 mm diameter
  3. 2.6 mm diameter
  4. 1.6 mm diameter
AnswerD. 1.6 mm diameter

Under Article 17, grounding conductors for Class C and D are annealed copper wire of 1.6 mm diameter or more (or corrosion-resistant metal wire with tensile strength of 0.39 kN or more). 1.0 mm and 1.2 mm are too thin. 2.6 mm can be used but is not the minimum.

Q33 | Voltage and grounding class

Which class of grounding is required for the metal frame of a three-phase 400 V motor? Assume no relaxation such as contact protection.

  1. Class D grounding (D種接地工事)
  2. Class A grounding (A種接地工事)
  3. Class C grounding (C種接地工事)
  4. Class B grounding (B種接地工事)
AnswerC. Class C grounding (C種接地工事)

Under Article 29, low-voltage equipment at 300 V or less needs Class D and above 300 V needs Class C. Three-phase 400 V exceeds 300 V, so Class C is required. Class A is for high and extra-high voltage equipment, and Class B is for the low-voltage side of transformers.

Q34 | When grounding cannot be omitted

For the metal case of 100 V equipment, in which case may grounding NOT be omitted?

  1. Installed in a wet place, with a 15 mA, 0.1 s current-operated earth leakage circuit breaker on the circuit
  2. Installed in a dry place
  3. The equipment has double insulation under the Electrical Appliance and Material Safety Act (電気用品安全法)
  4. Installed so that it is handled on a dry wooden floor
AnswerA. Installed in a wet place, with a 15 mA, 0.1 s current-operated earth leakage circuit breaker on the circuit

Omission using an earth leakage breaker (15 mA or less, 0.1 s or less, current-operated) is allowed only in places other than wet places, so it cannot be used in a wet place. Equipment of 150 V or less to earth in a dry place, double-insulated equipment, and equipment handled on a dry wooden floor may omit grounding under Article 29.

Q35 | Earth leakage breaker conditions

To omit grounding of low-voltage equipment installed somewhere other than a wet place by installing an earth leakage circuit breaker, which breaker condition is correct?

  1. Rated sensitivity 30 mA or less, operating time 0.1 s or less, current-operated
  2. Rated sensitivity 15 mA or less, operating time 0.1 s or less, current-operated
  3. Rated sensitivity 15 mA or less, operating time 0.5 s or less, current-operated
  4. Rated sensitivity 100 mA or less, operating time 0.1 s or less, current-operated
AnswerB. Rated sensitivity 15 mA or less, operating time 0.1 s or less, current-operated

Article 29 requires a current-operated breaker covered by the Electrical Appliance and Material Safety Act with rated sensitivity of 15 mA or less and operating time of 0.1 s or less. 30 mA and 100 mA are too large. 0.5 s is easily confused with the condition for relaxing grounding resistance to 500 Ω and is not the condition for omission.

Practice: answer the questions on this page

This practice tool asks questions in random order (it works when JavaScript is enabled). You can still read all the questions and explanations above without it.

* The explanations are for study purposes. Always check the Electrical Technician Examination Center's official announcements for how the exam is held, its scope and its pass mark. All questions are original questions written for this site, not real exam questions. Real electrical work must follow the law and requires the proper licence.

This page is a translation of the Japanese original. If the translation and the original differ, the Japanese version takes precedence. This translation was made with AI and may contain errors. Report a translation error View the Japanese original